How to apply different build cost rates to Use Class components of a development
In This Tutorial:
Overview of Appraisal!;
Using square meter Building Works costing;
Flexibility and detail in cost analysis;
Practical steps to build a development appraisal.
Summary:
This tutorial explores BOOM! Appraisal, focusing on the building works component. Learn how to use square meter building works costing to evaluate construction expenses for mixed-use developments. Discover how Appraisal provides flexibility in cost breakdowns, including external works, preliminaries, and contingencies, for detailed and adaptable project appraisals.
Exploring the Building Works Component in Appraisal
Step 1: Setting Up Your Project
Open Appraisal in BOOM!;
Select a hypothetical project, such as a mixed-use development including:
Class C3 (residential);
Sui Generis (co-living);
Class E (commercial);
View the project summary, noting key metrics like:
Development profit;
Return on GDV (e.g., 92% in the example).
Step 2: Calculating Building Works Costs
Navigate to the Building Works section;
Input Square Meter Costs for different use classes:
Class C3: £3,300/m² (35% of total GEA);
Sui Generis: £5,600/m² (60% of total GEA);
Class E: £2,250/m² (remaining 5% of GEA);
Adjust factors such as the GEA component to account for external walls.
Step 3: Adding External Works
Estimate the external works area (e.g., 2,000 m² for a 3,500 m² site with a 1,500 m² building footprint);
Input a fixed or per-square-meter cost (e.g., £2,500/m² for external works).
Step 4: Preliminaries, Overheads, and Profit
Add preliminaries as a percentage of building works (e.g., 8%);
Include main contractor overheads (e.g., 3%) and profit (e.g., 2%);
Optionally, add consultant fees (e.g., architect costs at 3% of building works).
Step 5: Contingency Planning
Define contingencies as fixed costs, per plot, or percentages;
Use per plot costs for simplicity (e.g., £2,500/plot).
Step 6: Review and Save
Review the total cost estimate (e.g., £28 million for building works and associated components);
Save the appraisal for future reference and refinement.
Why Use BOOM! for Building Works Analysis?
BOOM!’s appraisal tool offers unparalleled flexibility for:
Breaking down costs by use class and area;
Adapting to project-specific requirements;
Providing clear and actionable cost insights.